The re-grouting process at the Olympic Pool has been completed as has the cleaning and water proofing of the water channels and balancing tank. Changing the pool lights is being done at the moment
Work on the Melodi B4 pool has now begun
The pest control for rodents and cockroaches has been completed and is also ongoing
Cutting of the grass and watering on the Summer regime has begun
The burst pipes near Harmoni A14 were mended a couple of weeks ago.
Yesterday (31 May) two further burst pipes were found and work is currently being done to mend these